Great Ormond Street Hospital Children’s Cancer Centre

Community Website

Completed Works

As of 21st April 2026, the secant piles, gantry piles and mini piles are now all complete on site.

Removal of the coring rig and completion of the coring.

In December 2025 we completed the demolition of level 01 basement slab.

To date we have installed 190 piles which forms part of the foundation for the new Children’s Cancer Centre.

The deconstruction of the Frontage Building was completed by July 2025.

February 2025 saw the completion of the Advanced works and the beginning of the deconstruction of the Frontage Building.